Project updates
Pavement Management Program (PMP)
The updates listed below refer to the Pavement Management Program (PMP) .
To find updates regarding other projects, go to major road construction
projects.
May 2012
May 18, 2012
2012-101 PMP Street Improvement Project
A pre-construction conference was held on May 17.
-
American Blvd
(between W 82nd St and Xerxes Ave)
The Contractor is anticipating starting with removals in this area the week of May 28.
-
Normandale Service Rd
(between W 84th St and American Blvd)
The Contractor is anticipating starting with removals and storm sewer work in this
area the week of May 28.
-
W 81st Street
(between Pleasant Ave and Nicollet Ave)
The Contractor is anticipating starting with removals in this area the week of May 28.
-
W 83rd Street
(between Emerson Ave and Aldrich Ave)
The Contractor is anticipating starting with removals in this area the week of May 28.
-
Thomas Lane
(between W 81st St and W 80th St)
Centerpoint Energy anticipates starting gas service work in this area the week of May
21.
2012-102 PMP Street Maintenance Project
-
Xavier Area
(between Normandale Boulevard and Vessey Avenue includes Vessey Avenue, Overlook Drive
between Normandale Boulevard and Vessey Avenue and all circles and
courts)
The Contractor has finished street patching by new curb and manholes. The Contractor
began milling and bituminous paving. Boulevard restoration will be completed the week
of May 14th. Bituminous paving will be completed early in the week.
-
Multi Modal Trail
(along Auto Club Road and Normandale Boulevard between Zion Road and 110th
Street)
The Contractor has begun boulevard restoration. The Contractor will continue boulevard
restoration the week of May 14th.
-
Auto Club Road
(between railroad bridge and Normandale Boulevard)
Concrete work has been completed. Boulevard restoration will begin the week of May
14th. The Contractor will begin to raise manholes and gate valves to street elevation.
Milling and bituminous paving will begin early in the week. Lane changes will occur
throughout the week.
-
Normandale Boulevard
(between Auto Club Road and 110th Street)
Concrete work has been completed. Boulevard restoration will begin the week of May
14th. The Contractor will begin to raise manholes and gate valves to street elevation.
Milling and bituminous paving will begin early in the week. Lane changes will occur
throughout the week.
-
Overlook Drive
(between Rich Road and France Avenue)
The Contractor will continue adjusting manholes and gate valves. Concrete removals
will begin the week of May 14th along with concrete work. Outside lanes will be closed.
-
Kingsdale Area
(between Poplar Bridge Road including Nine Oaks Circle and Forest Hills
Circle)
City staff will begin marking for removals the week of May 14th.
-
102nd Street
(between Xerxes Avenue and Penn Avenue)
CenterPoint Energy will continue gas main work the week of May 14th.
May 11, 2012
2012-101 PMP Street Improvement Project
A pre-construction conference is scheduled for May 17. Construction is anticipated to start
in late May - early June.
2012-102 PMP Street Maintenance Project
-
Xavier Area
(between Normandale Boulevard and Vessey Avenue includes Vessey Avenue, Overlook Drive
between Normandale Boulevard and Vessey Avenue and all circles and
courts)
The Contractor has finished street patching by new curb and manholes. The Contractor
began milling and bituminous paving. Boulevard restoration will be completed the week
of May 14th. Bituminous paving will be completed early in the week.
-
Multi Modal Trail
(along Auto Club Road and Normandale Boulevard between Zion Road and 110th
Street)
The Contractor has begun boulevard restoration. The Contractor will continue boulevard
restoration the week of May 14th.
-
Auto Club Road
(between railroad bridge and Normandale Boulevard)
Concrete work has been completed. Boulevard restoration will begin the week of May
14th. The Contractor will begin to raise manholes and gate valves to street elevation.
Milling and bituminous paving will begin early in the week. Lane changes will occur
throughout the week.
-
Normandale Boulevard
(between Auto Club Road and 110th Street)
Concrete work has been completed. Boulevard restoration will begin the week of May
14th. The Contractor will begin to raise manholes and gate valves to street elevation.
Milling and bituminous paving will begin early in the week. Lane changes will occur
throughout the week.
-
Overlook Drive
(between Rich Road and France Avenue)
The Contractor will continue adjusting manholes and gate valves. Concrete removals
will begin the week of May 14th along with concrete work. Outside lanes will be closed.
-
Kingsdale Area
(between Poplar Bridge Road including Nine Oaks Circle and Forest Hills
Circle)
City staff will begin marking for removals the week of May 14th.
-
102nd Street
(between Xerxes Avenue and Penn Avenue)
CenterPoint Energy will continue gas main work the week of May 14th.
May 4, 2012
2012-102 PMP Street Maintenance Project
-
Xavier Area
(between Normandale Boulevard and Vessey Avenue includes Vessey Avenue, Overlook Drive
between Normandale Boulevard and Vessey Avenue and all circles and
courts)
The Contractor has finished concrete, storm sewer and sanitary sewer work. Raising of
all manholes and gate valves to meet final street grade is complete. Street patching by
new curb and manholes is nearly complete and will finish early in the week of May 7th.
Boulevard restoration will continue the week of May 7th and the Contractor anticipates
milling the Xavier area late in the week with bituminous paving to follow.
-
Multi Modal Trail
(along Auto Club Road and Normandale Boulevard between Zion Road and 110th
Street)
The Contractor will continue boulevard restoration the week of May 7th.
-
Auto Club Road
(between railroad bridge and Normandale Boulevard)
Storm sewer and sanitary sewer manhole work is complete. Concrete work will continue
the week of May 7th. The outside lanes will continue to be closed.
-
Normandale Boulevard
(between Auto Club Road and 110th Street)
Storm sewer and sanitary sewer manhole repairs are complete. Concrete work will
continue the week of May 7th. The outside lanes will continue to be closed.
-
Overlook Drive
(between Rich Road and France Avenue)
CenterPoint Energy plans to complete work in the area Friday, May 4th. The Contractor
plans to begin adjusting manholes and gate valves the week of May 7th with the inner
lanes being closed for adjusting on Monday, May 7th and then switching to the outer
lanes being closed upon completion of the inner lanes.
-
Kingsdale Area
(between Poplar Bridge Road including Nine Oaks Circle and Forest Hills
Circle)
CenterPoint Energy will continue gas service work the week of May 7th.
-
102nd Street
(between Xerxes Avenue and Penn Avenue)
CenterPoint Energy will continue gas service work the week of May 7th.
April 2012
April 30, 2012
2012-102 PMP Street Maintenance Project
-
Xavier Area
Raising of all manholes and gate valves to meet final street grade will occur the week
of April 30th. Also, street patching by new curb and manholes will be finished. The
contract will begin clean up and boulevard restoration late in the week of April 30th.
-
Multi Modal Trail
Trail will continue to be closed. The Contractor will start restoration along the
trail and pour pedestrian ramps.
-
Auto Club Area
The Contractor will continue working on storm sewer and sanitary sewer manhole repairs
along with concrete work. The outside lanes will continue to be closed.
-
Normandale Boulevard Area
The Contractor will continue working on storm sewer and sanitary sewer manhole repairs
along with concrete work. The outside lanes will continue to be closed.
-
Overlook Drive Area
CenterPoint Energy will continue work throughout the area.
-
Kingsdale Area
(between Poplar Bridge Road including Nine Oaks Circle and Forest Hills
Circle)
CenterPoint Energy anticipates beginning gas service work the week of April 30th.
-
102nd Street
(between Xerxes Avenue and Penn Avenue)
CenterPoint Energy anticipates beginning gas main work the week of April 30th.
April 20, 2012
2012-102 PMP Street Maintenance Project
-
Xavier Area
The Contractor will continue pouring curb, sidewalk and driveways the week of April
23rd. Work on storm sewer and sanitary sewer manholes will continue.
-
Multi Modal Trail
Trail will continue to be closed. The Contractor will continue work on trail and is
expected to pave the trail late in the week of April 23rd.
-
Auto Club Area
The Contractor expects to switch traffic control by closing the outside lanes and open
the inside lanes to traffic the week of April 23rd. Storm sewer and sanitary sewer
manhole repair will continue along with curb removal.
-
Normandale Boulevard Area
The Contractor expects to switch traffic control by closing the outside lanes and open
the inside lanes to traffic the week of April 23rd. Storm sewer and sanitary sewer
manhole repair will continue along with curb removal.
-
Overlook Drive Area
CenterPoint Energy will continue work throughout the area.
April 13, 2012
2012-102 PMP Street Maintenance Project
-
Xavier Area
The Contractor anticipates starting work on the project the week of April 16.
-
Multi Modal Trail
The Contractor anticipates starting work on the project the week of April 16.
-
Auto Club Area
Advanced warning signs have been placed indicating work starting April 18. CenterPoint
Energy will continue work throughout the area.
-
Normandale Boulevard Area
Advanced warning signs have been placed indicating work starting April 18. CenterPoint
Energy will continue work throughout the area.
-
Overlook Drive Area
CenterPoint Energy will continue work throughout the area.
-
Chalet Road Area
City staff will continue marking the street for various removals and repairs including
curb and storm sewer.
-
Maryland Road Area
City staff will continue marking the street for various removals and repairs including
curb and storm sewer.
April 6, 2012
2012-102 PMP Street Maintenance Project
The pre-construction conference was held Wednesday, April 4.
-
Xavier Area
The Contractor anticipates starting work on the project the week of April 9.
-
Multi Modal Trail
The Contractor anticipates starting work on the project the week of April 9.
-
Auto Club Area
CenterPoint Energy anticipates beginning gas service work the week of April 9.
-
Normandale Boulevard Area
CenterPoint Energy anticipates beginning gas service work the week of April 9.
-
Overlook Drive Area
CenterPoint Energy anticipates beginning gas service work the week of April 9.
-
Chalet Road Area
City staff will begin marking the street for various removals and repairs including
curb and storm sewer in the week of April 9.
March 2012
March 30, 2012
2012-102 PMP Street Maintenance Project
A preconstruction conference is schedule for the week of April 2nd.
-
Maryland Area
City staff has marked the street for various removals and repairs including curb and
storm sewer.
-
Auto Club Area
City staff has marked the street for various removals and repairs including curb and
storm sewer.
-
Normandale Boulevard Area
City staff has marked the street for various removals and repairs including curb and
storm sewer.
-
Xavier Area
City staff has started marking the street for various removals and repairs including
curb and storm sewer.
-
Overlook Drive Area
City staff will begin marking the street for various removals and repairs including
curb and storm sewer in the week of April 2.
-
102nd Street Area
City staff will begin marking the street for various removals and repairs including
curb and storm sewer in the week of April 2.
For more information, contact:
Shelly Pederson, City Engineer
1700 W. 98th Street
PH: 952-563-4870, FAX: 952-563-4868
E-mail: engineering@ci.bloomington.mn.us
Streets HOME |
Current projects |
PMP |
Specifications
|
|
|
|
|